Method of evaluation - Tenders

No obligation for the contracting authority to specify in the call for tenders the method of evaluation

In the case of a public service contract to be awarded pursuant to the criterion of the most economically advantageous tender in the opinion of the contracting authority, that authority is not required to bring to the attention of potential tenderers, in the contract notice or the tender specifications relating to the contract at issue, the method of evaluation used by the contracting authority in order to specifically evaluate and rank the tenders. However, that method may not have the effect of altering the award criteria and their relative weighting.

CJEU, c-6/15, 14 July 2016

Associated areas of specialisation: Public procurement and PPP